Project Details

Devon Research Facility Lab A152 Fit Up

Devon Research Facility Lab A152 Fit Up

Project Description: Prologic Construction Ltd., in collaboration with InnoTech Alberta and Fox Engineering, completed a specialized renovation of Lab A152 in Devon to enhance its functionality and safety.

The project involved the installation of an owner-supplied fume hood along with a comprehensive interior renovation tailored to meet the technical requirements of the lab environment.

The scope of work included demolition, HVAC modifications, plumbing, electrical and control systems, drywall, painting, mechanical upgrades, and custom millwork and casework

Construction Gallery

PROJECT DETAILS

Project Type: Renovation
Final Value: $116,000
Total Project Duration: 3 Months
Construction Duration: 3 Months
Completion: April 2019

PROLOGIC TEAM

Project Manager – Joel Amyotte
Project Coordinator – Harshpreet Grewal
Site Superintendent- Dennis Lilley
General Superintendent- Wayne Hansen

Project Completion & Impact

Prologic’s attention to detail and expertise in handling complex lab environments ensured that the renovation was completed to the highest standards, providing InnoTech Alberta with a modernized and safe workspace.