Project Description: Prologic Construction Ltd. successfully completed a comprehensive renovation of the Leduc Composite lab, transforming the space to meet modern educational and operational standards. The project involved the complete removal of all existing components, followed by the installation of new infrastructure, including gas lines, water lines, and custom millwork.

A portion of the floor was removed to connect to existing services, ensuring that gas and electrical supplies were effectively routed to each workstation. Once the renovations were finalized, new flooring was installed, and all millwork was completed alongside the necessary mechanical work, resulting in a state-of-the-art laboratory space.

Construction Gallery

PROJECT DETAILS

Project Type: Interior Renovation
Location: Leduc, AB
Final Value: $209,413
Total Project Duration: 2 Months
Completion: September 2020

PROLOGIC TEAM

Project Manager – Adil Quadri
Project Coordinator – Margaret Moher
Site Superintendent- James Webber
General Superintendent- Bill Durnford

MITIGATION STRATEGIES & SOLUTIONS:

Detailed planning and coordination were essential, particularly in scheduling the removal and installation of systems to ensure a seamless transition between phases. By collaborating closely with all stakeholders, we ensured timely communication regarding any adjustments needed for the gas and water lines. Our team also prioritized the structural integrity of the space during floor removal, utilizing experienced contractors to minimize disruption. These strategies enabled us to successfully complete the project on time and within budget while achieving the high-quality standards expected by the client.